
Footing escavation
A large footing is installed. First the a hole is dug down to add concrete.

Gravel and re-bar
Some gravel and re-bar is added before concrete.

concrete
Finally concrete will fill the 18" cube

Smartjack attached
A galvanized Smartjack is attached to the footing.

W-8 beam
This is not the usual beam that Omni installs but this is what the engineer spe'd out

Adjustment
The Smartjack features a large adjustment

Smartjacks and re-concrete
The Smartjacks are in place and the floor is re-concreted back.

Support for stair cavity
The beam is located next to the stairwell where the floor is at it's weakest.